Sunday, October 13, 2019

Modernization Program Project Management

Modernization Program Project Management Interrelated duties or tasks implemented within a certain time in a fixed period on a certain cost with other limitations following a certain strategy is known as project (Dictionary.com (2016), occasionally these projects have been outsourced to a specialized outsourcing companies which are specialized in project management, in order to maximize their efficiency within available resources. Being employed by a consultancy firm, I have been given a task to complete a consultancy report so the company can reemploy and execute its Modernization Program. The report will help to identify and rectify the best abilities being executed on the basis of the detailed set of the tasks explained in this report. All the analysis and the evaluation of the said program to cover all the aspects of the execution will be provided. The relationship between the firm and Remploy will be strengthened by implemented the required changes. Reason The general objective of this venture is to modernize Remploy processing plants that are being worked by debilitated individuals to limit operational cost. Another objective is to augment the general effectiveness of all Remploy manufacturing plants by diminishing the reliance on individuals and limiting general blunders that may happen. The change must be made in a manner that the representatives dont feel constrained or debilitated by this modernization. The extent must be finished inside the given spending plan.[G9][G10] Employees must be acceptable, moved and remuneration must be given to the individuals who are not willing to acknowledge this change.[G11][G12] To guarantee that Remploy and its representatives are happy with the general execution of the program. This must be done gently. Scope Remploy is in charge of the work of crippled individuals all through the Assembled Kingdom. This includes extraordinary abilities with a specific end goal to handle incapacitated individuals and help their reintegration in the general public. Remploy has been practical since the finish of World War II and from that point forward they have been in charge of making and giving employments to a large number of impaired individuals. Through this modernization program, Remploy means to make more occupations and increment the number of individuals utilized while keeping the spending restricted. This has been remembered and a Gantt diagram has been made to meet the given time span of the venture.[G13][G14][G15] An exhaustive arrangement has additionally been set up to guarantee a smooth and simple move of Remploy to a more current working environment. This reintegration is aided by the given spending plan on which light will be shed also in this report. Objectives The program plan for this report diagrams the essential undertakings that will be required to start, arrange and execute the program for Remploy. This will likewise incorporate a definite design of the arranging of the program which will be the urgent piece of this program. All dates are well thought and plainly named. Gantt Chart S. No Task Number Task Name Start Date End Date Duration 1 1 Initialization of the program[G17] 2/1/2017 26/1/2017 20 days 2 1.1 Scope definition 2/1/2017 7/1/2017 6 days 3 1.2 Identification of roles 10/1/2017 15/1/2017 6 days 4 1.3 Finalization and Gain of approval 17/1/2017 26/1/2017 8 days 5 2 Planning of the project 27/1/2017 24/4/2017 62 days 6 2.1 Development of a plan 27/1/2017 16/3/2017 35 days 7 2.1.1 Work breakdown structure development 27/1/2017 7/2/2017 8 days 8 2.1.2 Program staffing plan 8/2/2017 16/2/2017 7 days 9 2.1.3 Program schedule plan 17/2/2017 2/3/2017 10 days 10 2.1.4 Project budget development 3/3/2017 16/3/2017 10 days 11 2.2 Project Control Plan Development 17/3/2017 24/4/2017 27 days 12 2.2.1 Technical assistance development 17/3/2017 28/3/2017 8 days 13 2.2.2 Quality management plan 29/3/2017 6/4/2017 7 days 14 2.2.3 Contingency management plan 7/4/2017 17/4/2017 7 days 15 2.3 Finalization and Gain of approval 18/4/2017 24/4/2017 5 days 16 3 Execution of the Project 25/4/2017 25/4/2021 1044 days 17 3.1 Phase One 18 3.2 Phase Two 19 3.3 Phase Three The program plan for this report diagrams the essential tasks that will be required to start, arrange and execute the program for Remploy. This will likewise incorporate a nitty gritty design of the arranging of the program which will be the critical piece of this program. All dates are well thought and plainly marked. The execution of the project will be done in three basic stages that have been estimated to take around 3-4 years depending on the number of working days and the efficiency of execution. The stages are in line with the case study of Remploy which breaks it down to its core levels. The manpower to be used has not been highlighted in the chart due to its vast and immense execution. This will need a more thoroughly thought plan to be done during the planning phase of the program. The execution phases have been described below: Phase 1 Closing of sites that have been selected for the program Transfer of employees and equipment to a new site Phase 2 Reintegration of employees in the new environment Restarting business in the new sites using transferred equipment and employees Phase 3 Help change the mindset of employees and speed up the progress of business by helping them settle down in the new environment Ensure that the business operates competitively and efficiently with the market and all legislations are satisfied COST ESTIMATION A comprehensive budget provides management with an understanding of how funds will be utilized and expanded over time for projects or operations (Insight ®, 1997). [G18]The budget for the five-year plan has been set around 555[G19] million pounds by the department of work and pension. The Minister for disabled people had set out this budget in order to reduce costs by modernization and helping disabled people compete with the competitive market. The breakdown of this budget is shown below. It should be kept in mind that Remploy is responsible for 84 factories that need to be modernized and employees relocated, therefore, the execution of the project is bound to use the maximum amount of [G20][G21]allotted money. The amount of money that remains can be used to compensate and make up for any damage that may be incurred during the implementation of the project.[G22] Task No. Item Cost (GBP) 1 Initialization of the project 100,000 1.1 Identification and Development of personnel 100,000 2 Planning of the program[G23] 11,000,000 2.1 Development of a plan 500,000 2.2 Development of project control plan 500,000 2.3 Finalization of the program[G24] 100,000 3 Execution of the program[G25] 268,000,000 3.1 Phase one 168,000,000 3.2 Phase two 50,000,000 3.3 Phase three 50,000,000 Total 279,100,000 Advantage administration arranges required to determine the advantages that will be conveyed by the usage of a venture or a program (Benefit administration arrange layout activity, 2015). In this report, an intensive advantage administration arrange has been created to guarantee that the turning points are unmistakably delineated and distinguished to guarantee that the program is on track with its encouraging. Without an advantages administration program, this report would pass up a great opportunity for one of the vital elements that should be distinguished and fill in as a reason for the execution of the program. One such advantage and encouraging to accomplishment have been laid out in the table beneath while utilizing key execution pointer as a help screen the viable use of accomplishing business destinations (Inc, 2016).[G26] BENEFIT: Reduction in operational cost KPI: Liquidity and cash flow improvement Measure Baseline Value (dd/mm/yyyy) Target Value (dd/mm/yyyy) Interim target No Source Monthly cost Reporting Forum Bi-monthly report Start date Frequency Every two months End date When will reporting finish (dd/mm/yy)?[G27] Responsibility for reporting Name Position Factory supervisor Organisation Remploy Dangers are constantly present when the usage of another program is considered. This hazard must be imagined and distinguished by the venture administration group to guarantee that the administration can handle and moderate any dangers without bringing on any money related weight. The dangers distinguished are ordinarily overseen by the firm all through the usefulness of the firm which makes is simpler for them to be taken care of. As a specialist, we are pleased with our capacity to prepare for time and deal with the program at each progression of the arrangement.[G28][G29][G30] Risk Risk Level Likelihood Mitigation Strategy Hours per person High Certain A comprehensive management approach must be applied Programme Schedule High Certain Strict policy of implementation and extra days kept for delays and losses Project deliverables Low Likely to some extent Deliverables are clear to all parties. Will be reinforced from time to time Lack of commitment Low Unlikely Team is motivated to ensure a smooth transition Media and Political pressure Medium Uncertain Constant update and communication with stakeholders and media personnel Loss of individuals Low Unlikely Retention and bonus payments provided to key individuals to keep them motivated Partner administration is the way toward dealing with the desire of any individual who has an enthusiasm for a venture or will be influenced by it and is a key initiative instrument. At the point when there is a cognizant and organized drawn nearer, partner administration secures the possession and responsibility fundamental for conveying changes (Board, no date). The accompanying graphs portray the partner administration and correspondence arranges altogether [G31]that will be actualized to guarantee that correspondence between the venture administration group and the group of Remploy will be all around educated at all time. Stakeholders need to be identified and informed about the processes going on within the program. These stakeholders are as following: Project management consultant HR team of Remploy Remploy financial experts Remploy operational expert Remploy management Equipment suppliers Office of Minister for disabled persons Equipment suppliers and contractors Employees of Remploy The following matrix shows the distribution of the above-mentioned stakeholders for the modernization program to be implemented by Remploy.   Ã‚   Introduction According to Management Guide.com, a project management framework is a subset of tasks, tools, and templates used in combination by the team to envision the major elements of the projects which ar[G34]e needed to initiate a program (Guide, 2010). These elements ensure that the resources such as money, employees, equipment and time are used to their maximum potential by efficient planning, implementation, and control. This ensures that the deliverables of the project are achieved on time which helps the overall p[G35]rogress of the program. There are numerous frameworks that are used in the business world today which are there to aid the project management team to work their way around a project. These frameworks include the Risk management framework, Change management frame[G36]work, Process based management framework and lean management framework. It is not easy to decide which framework to work with since there are numerous businesses with multiple deliverables and no framework is proven to produce the best result. Two or more frameworks can sometimes be merged by a manager depending on their requirements. Two frameworks that will be discussed for this project are Change management framework and Risk management framework. The advantages, disadvantages and critical analysis of each framework are discussed below. CRITICAL JUSTIFICATION Risk Management framework Risk management framework identifies the risks involved in the project with respect to stakeholders and provides a detailed analysis of each risk. The risk management framework is widely used due to its vast application and capability of mitigating risks related to a project. The disadvantage of using this framework especially for this Modernization program would be the huge amount of expertise required to calculate and analyze all risks involved with the project. Since the program is scheduled to be implemented in five years, this can cause an, even more, uncertainty which would increase the cost related to expertise.[G37][G38][G39] Change Management framework Chance administration system distinguishes the dangers required in the venture as for partners and gives a point by point examination of each hazard. The hazard administration structure is broadly utilized because of its immense application and ability of moderating dangers identified with a venture. The detriment of utilizing this structure particularly for this Modernization program would be the enormous measure of ability required to compete and break down all dangers required with the venture. Since the program is planned to be actualized in five years, this can bring about a significantly more instability which would build the cost identified with skill.[G40][G41] Reflection and Conclusion (2016) in Available at: http://www.businessdictionary.com/definition/project.html (Accessed: 18 December 2016). Insight ®, P. (1997) Project management and the comprehensive project budget. Available at: http://www.projectinsight.net/project-management-basics/basic-project-budget (Accessed: 19 December 2016). Benefit management plan template initiative (2015) Available at: http://www.dtf.vic.gov.au/Publications/Investment-planning-and-evaluation-publications/Investment-management/Benefit-management-plan-template-Initiative (Accessed: 19 December 2016). Bourda, F. (no date) Tata Consultancy Services. Available at: http://www.tcs.com/SiteCollectionDocuments/White%20Papers/EntSol-Whitepaper-Stakeholder-Management-0713-1.pdf (Accessed: 19 December 2016). Inc, K. (2016) KPI examples. Available at: https://www.klipfolio.com/resources/kpi-examples#gref (Accessed: 19 December 2016). Guide, M.M. (2010) Project management framework: Definition and basic elements. Available at: http://www.mymanagementguide.com/project-management-framework-definition-and-elements/ (Accessed: 19 December 2016). Unknown (2010) Change management framework work process improvement Charles Sturt university. Available at: http://www.csu.edu.au/special/wpp/resources/change-management-framework (Accessed: 19 December 2016). [G1]Deleted:, [G2]Inserted: , [G3]Inserted: is [G4]Deleted:be [G5]Deleted:me [G6]Inserted: umber [G7]Deleted:qua [G8]Deleted:tity [G9]Inserted: t [G10]Deleted:d [G11]Inserted: e, [G12]Deleted:y [G13]Inserted: umber [G14]Deleted:qua [G15]Deleted:tity [G16]Deleted:d [G17]Deleted:me [G18]Inserted: a [G19]Inserted: [G20]Inserted: , [G21]Inserted: , [G22]Deleted:e [G23]Deleted:me [G24]Deleted:me [G25]Deleted:me [G26]Deleted:its [G27]Deleted:yy [G28]Inserted: r [G29]Inserted: f [G30]Deleted:f [G31]Inserted: s [G32]Inserted: the [G33]Inserted: the [G34]Inserted: , [G35]Inserted: , [G36]Inserted: to [G37]Inserted: , [G38]Inserted: , [G39]Deleted:me [G40]Inserted: e [G41]Deleted:u

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.